Dear GA members,
During the course of SPARTA’s first year, several change requests have been received:
* Effort adjustments (PM shifts, update of costs): CEA, IMT, CINI, MRU, and IST
* Cost adjustments (cost category change, budget transfer): CEA, YWH, and CNR
* Additions of new third-parties (linked, in-kind contribution): IND and CINI
* Minor fixes (deliverable description, milestone leader): CETIC, SMILE, and INOV
More details about each change can be found here:
https://sparta.technikon.com/03-WPs/WP13-Project-management/Amendment/83089…
and the complete amendment package is here:
https://sparta.technikon.com/03-WPs/WP13-Project-management/Amendment/
All those changes have been discussed and checked with the aforementioned partners, at the
Executive Board, and with the corresponding WP leaders, when relevant, to assess their
impact. This amendment request will be submitted to the Strategic Direction before being
sent to the European Commission.
Best regards,
--
Thibaud Antignac, Florent Kirchner, and Augustin Lemesle